In a case arising from an employment dispute, Brannock Berman & Seider convinced Florida’s Second District Court of Appeal to affirm a final judgment that was entered after the opposing litigant failed to follow the proper procedures to challenge an arbitration award.
Brannock Berman & Seider’s client, a successful local construction company, sued a former employee for breaching his employment agreement and tortiously interfering with the company’s business relationships. The case was referred to nonbinding arbitration, where the arbitrator ruled in favor of the company on all claims. The arbitrator also determined that the company was the prevailing party for awarding attorney’s fees and court costs.
After the arbitration decision was served, the employee filed a document requesting a trial de novo in circuit court. However, his filing did not expressly state that he was rejecting the arbitration decision. At the time, Florida Rule of Civil Procedure 1.820(h) required a party seeking a trial after nonbinding arbitration to file, within twenty days, both a notice rejecting the arbitration decision and a request for trial in the same document.
The company moved for final judgment, arguing that the employee had failed to comply with the rule. The trial court agreed and entered judgment for the company. The trial court also awarded fees. The employee appealed, arguing that the procedural rule conflicted with a Florida statute and violated separation of powers. After extensive briefing, the Second District affirmed the final judgment and awarded appellate fees, emphasizing the importance of strictly complying with the procedural rule.
The appellate decision represents a total victory for Brannock Berman & Seider’s client.